Task

Installation of 8 Wind Measuring Masts in total in the southwest of Bulgaria.

Challenge

Heavy snowfall impedes access to site and makes it difficult to carry out the installation as a matter of routine.

Additionally due to the weather conditions the danger of ice load has increased.

Procedure

With the help of a crawler, specially designed for this kind of projects, the material can be safely transported to site and be installed there. The crawler only causes minor soil pressure and can therefore also be used for humid areas and it only causes minor damage to farmland. Using special ropes/wires will reduce the danger of ice load.